Repair Tank 1086← Return to projects list

  • Client:
  • Year completed: 2004
  • Location: Baytown, TX
  • Service type: Tanks

About the project

Pala performed this complete replacement of the center deck of the floating roofWork also included the replacement of the rim bar (600LF) and foam dam (600 LF), 2160 SF of lap patches on the pontoons, 1150 SF of lap patches and bottom replacement, replacement of (2) 6” Pivot Master roof drains with sumps and supports, replacement of the bottom sump, installation of 1050 LF of 6” channel under deck stiffening, fabrication and installation of 25LF of 16” fill line, and miscellaneous piping and nozzle repair.

Pala worked a compressed schedule completing the scope in less than 9 weeks and was planned based on working (2) shifts of 4/10’s.

Pala used a unique fall prevention system to ensure safe demolition of the original structure and replacement of the new structure. The project was completed injury free.