MOTIVA CONVENT WET GAS SCRUBBER PROJECT
Convent, Louisiana
In 2006, Pala participated in the
erection of a wet gas scrubber at Motiva’s Convent, Louisiana
facility. The project had an initial value of $6 million, but as
other contractors fell behind schedule, Pala assumed additional
responsibilities, increasing the scope of its work by more than 200%
to over $18 million. When Pala assumed responsibility for
completion of the project, erection of the vessel was 66 days behind
schedule. Initially scheduled to work five 10-hour shifts weekly,
Pala agreed to work seven 12-hour shifts per week, plus eight weeks
of day and night shifts. Despite a four-week delay in materials
delivery and the issuance of 817 drawings after field installation
had begun, the Company regained 35 of the 66 days by the time of the
project’s completion.
The Company staffed 217 employees
in 11 disciplines at the project’s peak, and completed the project
with less than 1% craft rework and 10% productivity loss, despite a
workforce that was significantly depleted as a result of Hurricanes
Katrina and Rita. Due to the difficult environmental conditions and
size constraints, the client’s project manager expected 30%
productivity loss, with some contractors on the project experiencing
losses of more than 60%. Pala and the 25 subcontractors it managed
completed more than 300,000 man hours without a recordable injury,
making it the only contractor involved in the project to do so.
As a result of its excellent performance on the wet gas scrubber
project, Pala was recognized by both Motiva and Jacobs for its
employees’ attitudes, honesty, integrity and commitment to safety.
The Company received a 200% rating; equivalent to the Construction
Institute’s rating of “World-Class”, from Jacobs for the quality
control portion of its work.

EXXONMOBIL GULF COAST TANK FARM MAINTENANCE
Pala maintains a unit price
contract with ExxonMobil to provide all of its tank farm maintenance
and repair work in its Gulf Coast refineries. Pala was the first
tank maintenance provider to develop a process to execute work under
a unit-price agreement in cooperation with the customer. Using this
process, all tank repair activities are pre-priced and based on a
cost per unit. This shortens procurement lead-times and provides
the client with a more controllable budget. One of the Company’s
major clients believes that by utilizing Pala as its single-source
provider of tank farm maintenance and repairs in these facilities,
it achieves 14% total maintenance cost savings and a seven to ten
week time savings on an average tank turnaround.
An example of Pala’s ability to provide superior service with short
lead-times was the “GH-101” tank in ExxonMobil’s Baytown, TX
refinery. The Company was contacted on a Friday afternoon in
October 2006 to remove and replace a bladder inside the 3,000-pound
gas holder. Exxon estimated that each day the tank was offline cost
the facility $200,000 and was therefore adamant that the project be
completed on time. Pala had never before performed a bladder job
and was unfamiliar with the tools necessary to perform the work.
Despite its lack
of direct experience, two full days of rain delay and a complete
shift dedicated to rework as a result of a facility procurement
problem, the Company completed the project ahead of schedule, under
budget and with zero safety infractions. Pala managed to accomplish
the whole job in nine days of two, 12-hour shifts; the previous
contractor had taken 12 days with twice as many workers for the same
scope of work.
NASA’S
MICHOUD ASSEMBLY FACILITY LOCKHEED MARTIN CORPORATION - REHAB FINAL
ASSEMBLY, BLDG. 103 PROJECT
New
Orleans, Louisiana
As the successful bidder of this
$10.6 million competitively bid lump sum project, Pala accepted the
challenges of this schedule driven twelve month project. The scope
included installation of roof top air conditioning equipment, a new
breathing air system, and piping systems installed at a 60’
elevation in the 44 acre building. Scheduling and coordination of
large subcontracts including electrical, instrumentation,
insulation, sheetmetal ducting, and asbestos removal were critical
to the overall project success.
Pala successfully met the project
completion schedule, as well as achieving numerous milestone
completion dates, despite significant delays due to the ongoing
space shuttle tank fabrication operations.
Pala was also completing another $7
million of construction projects at the site currently with the
Final Assembly Project.
MOTIVA NORCO FELICIANA PIPELINE PROJECT
Norco,
Louisiana
The Feliciana Pipeline project in
Motiva’s Norco, LA facility presented unique challenges for Pala.
The project had an original value of $4 million, which grew to $8.25
million by completion. When the project timeline had to be
accelerated due to the expected completion of a related pipeline,
Pala’s team developed a creative solution to debottleneck the
facility’s large gas blender in time for the completion of the
related pipeline. The Company
performed approximately 144,000 manhours with a peak labor force of
150 people. Pala’s efforts led to a leak-free start-up and met the
accelerated timeline despite 544 field change orders.
BORDEN
CHEMICAL, INC.,
Geisimar,
Louisiana
NEW
FORMALDEHYDE PLANT PROJECT:
In 2000, Pala performed the design and
construction on a new $27 million total installed cost formaldehyde
plant in Geismar, Louisiana for Borden Chemicals. The project’s
scope included all related civil, structural, equipment and piping
work at a total price of $8.1 million.
The project began five months later
than originally scheduled due to permitting issues and Pala arranged
to field erect tanks to regain eight weeks of the lost time. The
Company’s employees performed nearly 70% of the work and completed
construction two weeks of ahead of schedule with no issues on
start-up. Pala was awarded the Associated Builders and Contractors
(“ABC”) Eagle Award for Excellence in Construction for its execution
of the project.
|