|
|
BORDEN
CHEMICAL, INC
NEW FORMALDEHYDE PLANT PROJECT |
|
 |
|
New Formaldehyde Plant Project
|
Project
Description: The Borden Chemicals, Inc. Formaldehyde Plant Project
completed by Pala-Interstate, LLC. presented new challenges and opportunities
for Pala-Interstate and it's project staff. The Formaldehyde Plant was
a Design build Project that involved the installation of the civil, structural,
equipment, and piping for two Formaldehyde units. The project also included
tank farms, roads, offices, load out facilities and a rail spur to accommodate
the storage and distribution needs of three Formaldehyde units. With a
final price tag of $8,140,000 and Pala self performing just over 68% of
all work, the plant started up two weeks ahead of schedule and flawlessly.
The Borden Chemical Inc. facility upon completion, was designed to produce
600,000 pounds of 50% concentrated formaldehyde and 1,800,000 pounds of
UFC. Distribution of the product was to be handled through pipeline, trucking
and rail cars.
The
plant is located on the Mississippi River Road near Geismar, Louisiana.
The site started out as a nine acre grass field with a few small tacks
and miscellaneous concrete pads that had to be demolished and removed.
Approximately 24,000 tons of fill material was brought in and spread to
raise four acres of the site an additional four feet. Shortly after this
was accomplished the site was put on hold while Borden Chemicals addressed
permit issues. Pala began to construct off satellites that would be used
to bring raw materials into the plant and deliver product to surrounding
clients while the EPA/DEQ permit issues were being handled.
The
completion of the permit issues took five moths to complete. This loss
of five months left Borden Chemicals in a very difficult position. The
first option, sliding the completion schedule back five months would mean
having to truck in product from Arkansas to fulfill it's contractual obligations
to its clients. The other option was to crunch the construction schedule
by five months.
Pile driving started August 30; two days after the permits were issued.
By the end of September, slabs were being formed and poured, To gain eight
weeks on the schedule, field erected tanks were being built on site, next
to the pads that were being constructed for their final destination. By
the end of October the majority of the structural steel was in place and
piping began.
November brought with it the majority of the equipment that would have
to be set, including two reactors, a catalytic incinerator and a one hundred
ten foot absorber column that was field dressed on rollers to reduce schedule
impact.
|
|
|
|
|
lsbl
#1 from east side
|
Rail
form loading
|
Second
road crossing from the
|
|
|
|
|
|
Truss
on the ground with pipe installed
|
Flying
the truss
|
Piperack
civil
|
Pala-Interstate, LLC - Diversified
Construction Services
Baton Rouge, LA (225) 272-5194 | New Orleans, LA (504) 468-1489 | La Porte, TX
(281) 470-7252
|
 |